First commissioning checklist

Fill in and print, or print a blank copy. Use the documentation for the exact model to confirm interfaces, capacity and setting limits.

Before you begin

01 · Communication: connect one device first

Confirm that the device and gateway acquisition side use the same protocol and compatible communication parameters. Establish the connection before adding points.

Verification target: stable communication with one known device.

02 · Point mapping: give both sides the same meaning

Map acquired registers, objects or variables to points the host system can use. Point names alone do not establish what a value means.

Verification target: a clear correspondence between device points and forwarded points.

03 · Live values: compare the device with the host system

Choose representative points that can be checked in the field. Observe whether changes travel correctly through the complete data connection.

Verification target: matching values with the same meaning and timing at each stage.

04 · Diagnostics & records: verify before expanding

Locate the affected part of the connection before adding more devices or points. Change one condition at a time.

Verification target: a configuration and verification record that can be reviewed later.

Checks when a problem occurs

No response or the device cannot be found

Communication works, but values are wrong or not updating

The gateway has data, but the host system cannot read it

Results & handover

Verify a few well-understood points before expanding the device and point counts.

Based on the website’s connectivity & commissioning guide. For items that do not apply, record the reason.